Step-by-Step Building Process — Timeline of Events*

1. Contract Signed, Down Payment Received
2. Contract to Lender to Start Loan Process
3. Applied for Architectural Approval
4. Lot Survey & Stakeout
5. Applied for Zoning, Septic & Building Permits
6. Owner Closes on Construction Loan
7. Meeting with Majestic Homes Inc. to Select Colors
8. Excavation of Foundation after all Permits Received
9. Footing Poured
10. Foundation Walls Installed
11. Bracing of Basement, Foam Insulation Installed
12. Backfill Basement after Inspection
13. I-Beam Installed
14. First Draw on Construction Loan Taken
by Builder
15. Lumber & Truss Delivered
16. Rough Carpentry, Windows & Exterior Doors Installed
17. Rough Heating & Sheet Metal
18. Roofing
19. Rough Plumbing
20. Rough Electrical
21. Fireplace Installed
22. 2nd Draw Taken
23. Rough Carpentry & Mechanical Inspections

24. Sewer/Septic Installed
25. Insulate
26. Siding & Stone/Brick Veneer Started
27. Exterior Painting & Caulking
28. Gutters Installed
29. Insulation Inspection
30. Concrete Floors Poured
31. Overhead Doors Installed
32. Drywall
33. 3rd Draw Taken
34. Finish Heating & Air Conditioner Installed
35. Interior Priming
36. Ceramic Tile/Marble, Wood & Vinyl Floors Installed
37. Finish Carpentry, Cabinets & Closet Shelving Installed
38. Countertops Installed
39. Interior Painting & Staining
40. 4th Draw Taken
41. Finish Plumbing
42. Mirrors & Shower Door Installed
43. Carpeting Installed
44. Walk-Thru with Builder
45. Final Close with Builder, Last Draw
46. Move in Performed by Owner

*Please note that this may not always be the exact order of operation at all new construction job sites, due to weather or change in materials.

Majestic Homes Inc. | 262-227-7975 or 262-227-7976 | Fax 262-623-6239

receive info | about us | contact us | testimonials | homes for sale | lots | models | standard features | building process | remodeling | home

© copyright Majestic Homes Inc. 2003 - 2010. All rights reserved. Site design by Eye 4 Graphics LLC